I. Use MS Project to develop a schedule and labor management report for an information system development project named Project EB1 at top level (you must have the name Project EB1 as the top level). Create WBS of subtasks by indentation with the following information: 

A. ProjectEB1

1. Initiation: 5 days, starting 9/14/2020: Shawn (80%) and Natasha (90%). Use Task Information – Resource Window to enter names and percentages of individuals performing each task. 

2. Planning: 7 days, starting one day before Initiation ended: Natasha (80%) and Shawn (75%). 

3. Execution: 10 days, starting the day after Planning completed. Shawn (100%), Jeff (90%), Yao (100%), Vang (90%) Ahmed (50%) and Nicole (90%). 

4. Testing: 10 days. All tests start at 8:00 AM in the morning of the day after Execution task ended: Shawn (70%), Jeff (90%), Chad (80%), Jack (80%) and Nicole (90%). 

6. Closing: 2 days, starting the morning of the day after Testing completed: Ming (90%), Nicole (70%), and Katie (80%). 

Note: Because all tasks end at 5:PM each day, a task which is scheduled to start one day before the end of another task will start at 8:00 AM on the same ending day of the other task. For example if task A is scheduled to complete at 5:00 PM on June 10 and task B is scheduled to start one day before task A’s completion, task B starting day will be June 10 at 8:00 AM. 

II. Use the Task Information-Predecessor Window to create the following links: 

FS (Finish to Start): Initiation to Planning, Planning to Execution, Execution to Testing, and Testing to Closing. Set a negative value to Lag Time to indicate time overlapping between two tasks. 

III. Insert the Baseline Start and Baseline Finish (without version number) columns before the Start column. Go to the Project tab, click Set Baseline, then click Update Project and set Start day of Initiation task to a day later. You will see the new dates in the start and finish date columns. Insert the Actual cost column to view the cost. If MS Project does not automatically move the remaining tasks (after Initiation) one day later, update all remaining tasks to start a day later.

IV. Go to the Task tab, click Tracking Gantt from the Gantt chart drop down list. You now see the tracking Gantt.

V. Print the Tracking Gantt report to PDF file which must include the following columns: Task name, Duration, Baseline start, Baseline Finish, Start, Finish, Predecessor, and Resource Names. You must have all columns shown. The report will spread multiple pages.

VI. Go to View tab, Other views, More views, Resource Usage and print to PDF this view. Review the PDF output to make sure that you don’t miss columns. Submit the PDF files to D2L.

Order a unique copy of this paper
(550 words)

Approximate price: $22

Basic features
  • Free title page and bibliography
  • Unlimited revisions
  • Plagiarism-free guarantee
  • Money-back guarantee
  • 24/7 support
On-demand options
  • Writer’s samples
  • Part-by-part delivery
  • Overnight delivery
  • Copies of used sources
  • Expert Proofreading
Paper format
  • 275 words per page
  • 12 pt Arial/Times New Roman
  • Double line spacing
  • Any citation style (APA, MLA, Chicago/Turabian, Harvard)

Our guarantees

We value our customers and so we ensure that what we do is 100% original..
With us you are guaranteed of quality work done by our qualified experts.Your information and everything that you do with us is kept completely confidential.

Money-back guarantee

You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.

Read more

Zero-plagiarism guarantee

The Product ordered is guaranteed to be original. Orders are checked by the most advanced anti-plagiarism software in the market to assure that the Product is 100% original. The Company has a zero tolerance policy for plagiarism.

Read more

Free-revision policy

The Free Revision policy is a courtesy service that the Company provides to help ensure Customer’s total satisfaction with the completed Order. To receive free revision the Company requires that the Customer provide the request within fourteen (14) days from the first completion date and within a period of thirty (30) days for dissertations.

Read more

Privacy policy

The Company is committed to protect the privacy of the Customer and it will never resell or share any of Customer’s personal information, including credit card data, with any third party. All the online transactions are processed through the secure and reliable online payment systems.

Read more

Fair-cooperation guarantee

By placing an order with us, you agree to the service we provide. We will endear to do all that it takes to deliver a comprehensive paper as per your requirements. We also count on your cooperation to ensure that we deliver on this mandate.

Read more

Calculate the price of your order

550 words
We'll send you the first draft for approval by September 11, 2018 at 10:52 AM
Total price:
$26
The price is based on these factors:
Academic level
Number of pages
Urgency