Project management ch 14 – project closure

Project Closure
Project Management Ch 14
6th Edition

Your Results:
The  answer for each question is indicated by a  .

 

1    
Which of the following is not a wrap-up closure activity that might be found on a checklist?
    A)
Getting delivery acceptance from the customer
    B)
Reassigning project team members
    C)
Closing accounts and seeing all bills are paid
    D)
Evaluation of team performance
    E)
Creating a final report
    

 
2    
The content of the final report typically includes the following topics EXCEPT
    A)
Lessons learned
    B)
Review and analysis
    C)
Recommendations
    D)
Executive summary
    E)
Team reviews
    

 
3    
When the project may be completed early with some parts of the project eliminated this is considered to be ___________ closure.
    A)
Normal
    B)
Premature
    C)
Perpetual
    D)
Changed Priority
    E)
Failed Project
    

 
4    
When a project starts with a high priority but it is cancelled because its rank erodes or crashes during its project life cycle, this is an example of what type of project closure?
    A)
Normal
    B)
Premature
    C)
Perpetual
    D)
Failed Project
    E)
Changed Priority
    

 
5    
Which of the following summarizes project performance and provides useful information for continuous improvement?
    A)
Customer acceptance
    B)
The final report
    C)
Team evaluation
    D)
360 degree feedback
    E)
Project summary
    

 
6 UNANSWERED   
Which part of the final report examines in detail the underlying causes of problems, issues, and successes relative to the project and includes concise, factual review statements of the project?
    A)
Executive summary
    B)
Review and analysis
    C)
Recommendations
    D)
Lessons learned
    E)
Appendix
    

 
7    
The purpose of project evaluation is to assess how well
    A)
The project team performed
    B)
The team members performed
    C)
The project manager performed
    D)
The project team and team members performed
    E)
The project team, team members and the project manager performed
    

 
8    
Which of the following would NOT be appropriate to assess when evaluating team performance?
    A)
How well the team performed in terms of time, cost, and specifications
    B)
Effectiveness of group decisions
    C)
Individual strengths and weaknesses
    D)
Customer satisfaction with project deliverables
    E)
Trust among group members
    

 
9    
An analysis carried out during and shortly after the project life cycle that attempts to capture positive and negative learning is represented in which of the following?
    A)
Scenario analysis
    B)
Variance analyses
    C)
Lessons learned
    D)
Performance evaluation
    E)
Strategic objectives
    

 
10    
The process for capturing lessons learned continues to evolve, but there are still many barriers to effectively capitalizing on lessons learned that have been identified. The following are examples of these barriers EXCEPT
    A)
Lack of time
    B)
Teams get little direction or support after lessons are reported
    C)
Lessons learned often degenerate into blame sessions
    D)
Lessons learned are being used across different locations
    E)
The organizational culture doesn’t support the effort that it takes to capitalize on lessons learned
    

 
11    
The following are distinguishing characteristics of retrospectives methodology EXCEPT
    A)
Uses an independent facilitator
    B)
Establishes in-process learning gates during the project life cycle
    C)
An owner, typically a team member, is assigned
    D)
Reviews cannot be linked to percent complete
    E)
A repository is developed that is easy to use
    

 
12    
A guide who leads the project team through an analysis of project activities that went well, what needs improvement, and development of a follow-up action plan with goals and accountability is a(n)
    A)
Owner
    B)
Project sponsor
    C)
Project manager
    D)
Facilitator
    E)
Mediator
    

 
13    
More and more companies are discarding the traditional superior-subordinate performance feedback process and replacing it with a multi-rater appraisal called
    A)
Critical incidences review
    B)
Management by objectives
    C)
The 360-degree feedback
    D)
Team evaluation survey
    E)
Retrospectives
    

 
14    
Which of the following is NOT a role of the closure facilitator?
    A)
Create an environment in which stakeholders feel safe to provide input
    B)
Lead the team in exploring new ways for solving problems
    C)
Uses several questionnaires as a starting point to conduct the post-project retrospective
    D)
Get delivery acceptance from the customer
    E)
Elicit a 360 degree view and input from all stakeholders to create a more complete picture of project issues
    

 
15    
Each retrospective is assigned a(n) _________, typically a team member who is very interested in and familiar with the retrospective. This individual will serve as the contact point for anyone needing information relating to the retrospective.
    A)
Owner
    B)
Project sponsor
    C)
Project manager
    D)
Facilitator
    E)
Mediator

 

Order a unique copy of this paper
(550 words)

Approximate price: $22

Basic features
  • Free title page and bibliography
  • Unlimited revisions
  • Plagiarism-free guarantee
  • Money-back guarantee
  • 24/7 support
On-demand options
  • Writer’s samples
  • Part-by-part delivery
  • Overnight delivery
  • Copies of used sources
  • Expert Proofreading
Paper format
  • 275 words per page
  • 12 pt Arial/Times New Roman
  • Double line spacing
  • Any citation style (APA, MLA, Chicago/Turabian, Harvard)

Our guarantees

We value our customers and so we ensure that what we do is 100% original..
With us you are guaranteed of quality work done by our qualified experts.Your information and everything that you do with us is kept completely confidential.

Money-back guarantee

You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.

Read more

Zero-plagiarism guarantee

The Product ordered is guaranteed to be original. Orders are checked by the most advanced anti-plagiarism software in the market to assure that the Product is 100% original. The Company has a zero tolerance policy for plagiarism.

Read more

Free-revision policy

The Free Revision policy is a courtesy service that the Company provides to help ensure Customer’s total satisfaction with the completed Order. To receive free revision the Company requires that the Customer provide the request within fourteen (14) days from the first completion date and within a period of thirty (30) days for dissertations.

Read more

Privacy policy

The Company is committed to protect the privacy of the Customer and it will never resell or share any of Customer’s personal information, including credit card data, with any third party. All the online transactions are processed through the secure and reliable online payment systems.

Read more

Fair-cooperation guarantee

By placing an order with us, you agree to the service we provide. We will endear to do all that it takes to deliver a comprehensive paper as per your requirements. We also count on your cooperation to ensure that we deliver on this mandate.

Read more

Calculate the price of your order

550 words
We'll send you the first draft for approval by September 11, 2018 at 10:52 AM
Total price:
$26
The price is based on these factors:
Academic level
Number of pages
Urgency